Facility remove- Qinghai Bridge
- Project :Facility remove- Qinghai Bridge
- Type :Highway Bridge
- Owner:Kaohsiung City Goverment
- Location:Kaohsiung City, Taiwan
- Method:Scaffolding assemble on the ground, and left with crane truck.
- Benefit:1. As a city develops, there is always construction. For an old city, the constructions often come with removing the old buildings. The same story happens in Kaohsiung City, Taiwan. When Kaohsiung railway underground project was completed and open traffic in October 2018. A cross-over railway bridge, Qinghai Bridge, ought to be demolished. Deadline: By February 16, 2019.
2. It is expected that the demolition of the bridge will take 12 days. Inevitably, a large amount of noise and dust will be generated by the demolition of the bridge. At the downtown of a 2.7 million population city that is not acceptable.
3. It was to reduce the inconvenience and avoid the noise and dust issue for the local residents. The government not only increased the large-scale demolished equipment number from 14 to 23 but also set a special plan. Instead of diminishing the bridge on-site, they manage a demolished way of cutting the bridge then lifted to another place to destroy.
4. SUCOOT as the shoring solution provider, need to pay extra attention to the loading. In addition to loading the bridges, it was vibrating during dismantle process, and various uncertainties also need to take into account. Therefore shoring as provided has to be possessed high strength and stable quality.
5. Sucoot's engineering team made careful calculation correspond to contractor required, SUCOOT provided shoring system to support the demolish case with guaranteed loading strength safety. Under the time pressure, Sucoot assembles the scaffolding on the ground and lift them with a crane to save time and beat the clock, so that the case can finish ahead of schedule.